TL;DR
One bedroom: 1 day. Whole main floor: 2–3 days. Full 3-bedroom home interior: 5–10 working days. Add 1–2 days for cabinet refinishing.
By project size
- →Single bedroom (walls + ceiling + trim): 1 day with a 2-person crew
- →Master bedroom + ensuite: 1.5–2 days
- →Kitchen (walls only, no cabinets): 1 day
- →Open-concept main floor: 2–3 days
- →Full 3-bedroom home interior: 5–8 days
- →Full 4+ bedroom home with detailed trim: 8–14 days
- →Cabinet refinishing (standard kitchen): 5–7 days including shop time
Why some quotes are 'one day' and others are five
- →A one-day quote for a full main floor usually means: one coat, no prep, no protection, and a sub-contracted crew rushing to the next job.
- →Proper prep alone is 40–60% of a paint job's time. A real timeline reflects that.
Living in the home during the project
- →Most clients stay in the home during interior projects. We work room-by-room so you always have a livable space.
- →Low-VOC paint means rooms are safe to re-occupy within hours, not days.
- →Kitchen-out-of-service time during cabinet refinishing: typically 5 days.
Common questions.
Yes, by request. Standard crews work Mon–Sat, 7am–6pm.
Last updated 2026-01-01← All guides